Program Scope

Comprehensive plan for the modernization and development of the 14 Regional Airports. The plan includes works comprised by Imminent New or Expansion Works and Imminent Refurbishment Works and development works for upgrading the airports’ facilities, which will contribute significantly to improving the overall customer travel experience, while responding to the expected increase in passenger traffic.
14 Airports to grow and develop
22 Terminals to be built, expanded and/or refurbished
4 Terminals to be demolished or decommissioned
15 Runways and associated maneuver areas to be
refurbished according  to EASA requirements
14 Airports get Initially Certified according
to EASA requirements

Tasks & Responsibilities

  • Management Consulting Services
  • Project Management Consulting Services
    • Establish PMO and PMO Coordination
    • Manage EASA Program Implementation
    • Support on Managing & Controlling Project Progress in relation 
to prescribed Timelines & Budgets
    • Work with BUs to ensure that project tracking, reporting 
and communication practices on projects and BUs 
are delivered consistently
    • Support on planning the Project Timelines
    • Provide Direction, Advice, Counsel and Mentoring to Project Team
    • Constantly Monitor and Report on Progress of the Project 
to all Stakeholders
    • Present Reports Defining Project Progress, Problems and Solutions
    • Project Evaluations and Assessment of Results
    • Risk & Opportunities Management-Assessment
  • Contract & Claims Management supporting services
  • Litigations, Technical Dispute Resolution and Arbitration Proceedings support
  • Interface with internal and external stakeholders including Management, Partners and Contractors.
  • Coordination with Public Authorities & Institutions

Customer

Fraport Greece S.A. (Concessionaire)

Country

Greece

Site

CLUSTER A: Kavala (KVA), Thessaloniki (SKG), Zakynthos (ZTH), Kefalonia (EFL), Aktion (PVK), Chania (CHQ), Corfu (CFU)] CLUSTER B: Skiathos (JSI), Mytilene (MJT), Samos (SMI), Mykonos (JMK), Santorini (JTR), Rhodes (RHO), Kos (KGS)]

Contractor

Intracom Constructions Société Anonyme Technical and Steel Constructions (INTRAKAT)

Independent Engineer

AECOM Limited

Period

2017-2025

Budget

Initial Capex of at least 415.0M€ until 2021 + 120.0M€ (2022 – 2025)