Cycladic Islands Interconnection with 
 the Hellenic Power Transmission System

Cycladic Islands Interconnection with 
 the Hellenic Power Transmission System

Program Scope

Engineering, Procurement, Civil and Electrical Works for
Project – Group A: Construction of an AC submarine cable link 150kV between Lavrio and Syros (approx. 108 km)
Project – Group B: Construction of AC submarine cable link 150 kV, 200 MVA AC cables between the islands: Syros-Paros (approx. 46 km) | Syros-Mykonos (approx. 35 km) | 
 Syros-Tinos (approx. 33 km)
Project – Group C: Construction of four (4) 150/20kV GIS Substations at Lavrio, Syros, Paros, and Mykonos MV, 
 LV Switchgear, Control – Protection – Automation and Telecommunication Systems
Project – Group D: Construction of one Static Variance Compensator (SVC) -100/+250MVar at Syros Island
 Maintenance for five years

Tasks & Responsibilities

  • Reporting to the IPTO CEO, CFO, Division Heads and IFIs
  • Lead the Planning and Implementation of the Program
  • Definition of Program’s Scope, Goals and Deliverables
according to contractual obligations
  • Develop full scale Program Plans
  • Manage & Control Projects Progress in relation 
to prescribed Timelines & Budgets
  • Provide Direction, Advise , Counsel and Mentoring 
to Project Team
  • Manage the daily operations of the projects
  • Constantly Monitor and Report on Progress 
of the Project to all Stakeholders
  • Present Reports Defining Project Progress, 
Problems and Solutions
  • Project Evaluations and Assessment of Results
  • Contract Management
  • Risk & Opportunities Management-Assessment
  • Claims Management / Dispute Resolutions
  • Interface with internal and external stakeholders including Management, Partners and Contractors.
  • Enhance engagement delivery excellence by ensuring that the Project/s Team/s are enabled consistently to deliver engagements on time, within budget and with high levels 
 of customer satisfaction.
  • Coordination with Public Authorities & Institutions

Customer

Independent Power Transmission 
Operator (IPTO)

Country

Greece

Site

Cyclades

Contractor

Prysmian Power link S.r.l (Group A  – Submarine Cable Link Lavrio SS – Syros SS) Hellenic Cables (Group B – Submarine Cable Links Syros – Paros , Syros – Mykonos , Syros – Tinos & HV Cable Terminal in Tinos) Consortium ALSTOM Grid S.p.A – ALSTOM Grid Hellas A.E. (Group C – 150 kV GIS Substations in Lavrio, Syros, Paros & Mykonos)
Consortium ABB A.B. – ABB A.E. (Group D – Static Variance Compensator SVC)

Period

2014 -2018

Budget

250 Mio€