Cycladic Islands Interconnection with the Hellenic Power Transmission System
Program Scope
Engineering, Procurement, Civil and Electrical Works for
Project – Group A: Construction of an AC submarine cable link 150kV between Lavrio and Syros (approx. 108 km)
Project – Group B: Construction of AC submarine cable link 150 kV, 200 MVA AC cables between the islands: Syros-Paros (approx. 46 km) | Syros-Mykonos (approx. 35 km) |
Syros-Tinos (approx. 33 km)
Project – Group C: Construction of four (4) 150/20kV GIS Substations at Lavrio, Syros, Paros, and Mykonos MV,
LV Switchgear, Control – Protection – Automation and Telecommunication Systems
Project – Group D: Construction of one Static Variance Compensator (SVC) -100/+250MVar at Syros Island
Maintenance for five years
Tasks & Responsibilities
- Reporting to the IPTO CEO, CFO, Division Heads and IFIs
- Lead the Planning and Implementation of the Program
- Definition of Program’s Scope, Goals and Deliverables according to contractual obligations
- Develop full scale Program Plans
- Manage & Control Projects Progress in relation to prescribed Timelines & Budgets
- Provide Direction, Advise , Counsel and Mentoring to Project Team
- Manage the daily operations of the projects
- Constantly Monitor and Report on Progress of the Project to all Stakeholders
- Present Reports Defining Project Progress, Problems and Solutions
- Project Evaluations and Assessment of Results
- Contract Management
- Risk & Opportunities Management-Assessment
- Claims Management / Dispute Resolutions
- Interface with internal and external stakeholders including Management, Partners and Contractors.
- Enhance engagement delivery excellence by ensuring that the Project/s Team/s are enabled consistently to deliver engagements on time, within budget and with high levels of customer satisfaction.
- Coordination with Public Authorities & Institutions
Customer
Independent Power Transmission Operator (IPTO)
Country
Greece
Site
Cyclades
Contractor
Prysmian Power link S.r.l (Group A – Submarine Cable Link Lavrio SS – Syros SS) Hellenic Cables (Group B – Submarine Cable Links Syros – Paros , Syros – Mykonos , Syros – Tinos & HV Cable Terminal in Tinos) Consortium ALSTOM Grid S.p.A – ALSTOM Grid Hellas A.E. (Group C – 150 kV GIS Substations in Lavrio, Syros, Paros & Mykonos)
Consortium ABB A.B. – ABB A.E. (Group D – Static Variance Compensator SVC)
Period
2014 -2018
Budget
250 Mio€