Wind Park Bogdanci – Lot 2 (Turn-Key / EPC Project)

PM_PARTNERS_PROJECTS-05

Program Scope

Design - Supply – Installation - Testing & Commissioning of Wind Park Bogdanci 36MW comprised by 16 Wind Turbines 2.3MW.
Construction of new AIS110/20kV Substation Bogdanci
Construction of 11.8km 110kV Transmission
Line Bogdanci – Valandovo
Construction of BoP and Access Road

Tasks & Responsibilities

  • Project Management
  • Initial Project Analysis and Planning
  • Value Engineering
  • Support in Design and Permits process
  • Technical Management & Coordination
  • Construction Management
  • Works Supervision
  • Change Orders administration & control
  • Claims Management
  • Contract Management
  • Procurement Management
  • Monitoring & Controlling Project Progress
  • Payments & Cost Management
  • Time Management
  • Quality Management
  • Health & Safety Management
  • Risk Management
  • Project Records Keeping
  • Completion Tests Inspection
  • Support in Project Closure & Hand Over procedures

Customer

ELEM AD Macedonian Power Plants

Country

North Macedonia

Site

Bogdanci

Contractor

Consortium Siemens SA - Terna Energy SA

IFI

German Development Bank (KfW)

Period

2012 -2014

Consultant

Fitchtner GmbH & Co. KG

Budget

Non Disclosed