Extension of Marfin Egnatia Bank Data Center

08005-ΜΕΒ ‘’Extension of Marfin Egnatia Bank Data Center ‘’

Location : Thermi–Thessaloniki/Greece
Year : 2008
Owner : Marfin Egnatia Bank
Contractor : ECS-Electric

Project Scope :

Design , Supply , Testing and Commissioning Civil , Electromechanical Works for
Upgrading of Existing Data Center

Construction of New Servers’ Room
Extension of Existing MV/LV Substation
Extension of AC/DC Batteries and Rectifiers Facilities
Data Room Cooling System
CCTV , Access Control and Security Systems

Assignment / Responsibility:

Project Management
Initial Project Analysis and Planning
Value Engineering
Support in Design and Permits process
Technical Management & Coordination
Construction Management
Works Supervision
Change Orders administration & control
Claims Management
Contract Management
Procurement Management
Monitoring & Controlling Project Progress
Payments & Cost Management
Time Management
Quality Management
Health & Safety Management
Risk Management
Project Records Keeping
Completion Tests Inspection
Support in Project Closure & Hand Over procedures